On July 7 in the morning, "built by tang electric co., LTD., jiangsu calderon joining into the nickel industry co., LTD. Investment in Indonesia in Kentucky self-provided power plant phase I project # 3 unit is connected to the grid is successful, the units is basic production operating conditions.
To ensure the smooth interconnection, the unit 3 tang electrical construction co., LTD., giving full play to the advantages of whole industry chain, cooperative engagement, closely monitor running status of equipment, carefully adjusting operation, to coordinate in advance, and the owners, management units and equipment manufacturers close contact, there is a flocculant is not to promote the grid work.